Dear Esteemed Investment Partner,
We are delighted to share the latest progress at Aviv Almasi as we continue moving steadily toward completing the project
This month we mark more significant milestones, with the development now 84% complete—a testament of the confidence and support of our valued investors and the project lead team.
📈 PROJECT PROGRESS
🏢 Structural & Finishing Works
Construction remains on schedule with excellent progress across all workstreams.
- ✅Swimming pool casted,awaiting additional coat of water proofing.
- ✅Gym,offices & working spaces walled awaiting roofing.
- ✅ Parapet walls erected plastered
- ✅ Masonry walling completed up to the 10th Floor
- ✅ Tiling ongoing on the 8th Floor
- ✅ Steel Windows and Door installation completed up to the 8th Floor
- ✅ Plumbing, CCTV & Electrical installations completed up to the 8th Floor
- ✅ Cabinetry installation completed up to the 7th Floor
- ✅Door locks installed up to 3rd floor
- ✅ Internal paint works 3rd floor
- ✅ Wooden door frame installation completed up to the 8th Floor
- ✅ Skimming and undercoat painting completed up to the 6th Floor
🏢 Infrastructure & Amenities
Significant progress has also been achieved on key infrastructure works.
- ✅ KPLC transformer and electricity meter applications submitted; and a contractor allocated by KPLC
- ✅ Borehole license has been issued
- ✅ Lift manufacturing completed; shipment to site is currently in progress
- ✅ Construction of the access road to the tarmac
🚀 LOOKING AHEAD
Over the coming weeks our key focus areas include:
- ✅ Swimming pool tiling
- ✅ Painting of the external walls
- ✅Installation of solar system
- ✅ Water treatment plant installation works
- ✅ Electrical cabling to proceed
- ✅ Final installation of windows and doors
🏡 SHOW HOUSE STILL OPEN
Our beautifully finished Show Houses are still open. Tell a friend to tell a friend to visit;
- ✨ Spacious layouts
- ✨ Premium finishes
- ✨ Quality workmanship
- ✨ The lifestyle and investment value that Aviv Almasi offers
🤝 INVESTOR REFERRAL PROGRAM
Thank you to all investors who continue recommending Aviv Almasi to family, friends, and colleagues.
💳 INVESTOR ACCOUNT UPDATE
We sincerely appreciate every investor who has remained committed to their payment plan. As the project advances into the intensive finishing phase, we kindly encourage you to;
- ☑️Review your account status
- ☑️ Keep scheduled instalments up to date
- ☑️ Top up deposits where applicable
- ☑️ Make arrangements to also clear the closing costs and sign your sale agreement.
💹Please note, apartments with outstanding arrears will be re-sold to other interested investors in our waiting list.
Timely payments play a vital role in maintaining construction momentum and ensuring successful project delivery.
For assistance regarding your investment at Almasi, our Team is always ready to assist.